SetTaskLineCurtain

Example

Purpose: Set up to 5 curtains for an individual task row.

It's possible to create up to 400 curtains on a single Milestones Professional schedule or template.

By default (without calling SetTaskLineCurtain), a curtain will span all of the tasks on the schedule and optionally in the date headings.

Once a curtain is named, it is limited to being a task line curtain.  Task line curtains will only appear if they are referenced via SetTaskLineCurtain.

Returns: none

Argument  

Type

Required

Purpose

1

Integer

Yes

Task Row (1 based)

2

Integer

Yes

Which curtain for line (1 - 5).  Up to 5 task line curtains can be set.  

3

String

Yes

Curtain name (if zero length or 1st character is blank, then remove)

4

String

No

Start date override.  

5

String

No

End date override.

 

 

 

 

 

Milestones Professional 2019 Automation Methods and Properties.  © Copyright 2018, KIDASA Software, Inc. All rights reserved.