Purpose: Set up to 5 curtains for an individual task row .
It's possible to create up to 400 curtains on a single Milestones Professional schedule or template.
By default (without calling SetTaskLineCurtain), a curtain will span all of the tasks on the schedule and optionally in the date headings .
Once a curtain is named, it is limited to being a task line curtain. Task line curtains will only appear if they are referenced via SetTaskLineCurtain.
Returns: none
Argument |
Type |
Required |
Purpose |
1 |
Integer |
Yes |
Task Row (1 based) |
2 |
Integer |
Yes |
Which curtain for line (1 - 5). Up to 5 task line curtains can be set. |
3 |
String |
Yes |
Curtain name (if zero length or 1st character is blank, then remove) |
4 |
String |
No |
Start date override. |
5 |
String |
No |
End date override. |