Answer:This can happen if a schedule is outlined and summary bars are turned on. The red bar is likely a summary bar. Solving the problem is easily done by either 1) Indenting the task so that it does not have any lower level tasks and correcting the outline structure of the schedule. or 2) Turning off summary bars. Determine if the task has lower level tasks:
Turn off Summary Bars:
|
|
|
|
Applies to Milestones Professional:
2017
2019
2021
2023
2025
The fast easy way to schedule your projects: Milestones Software by KIDASA Software, Inc. www.kidasa.com