Need to do a detailed 1-wk schedule

Question:     

I need to present a chart showing work performed on a project over the course of a week. I need to set up more than one entry per day per line.  I would like to be able to schedule work in 15 - 30 min increments. Is there any way to accomplish this with your software ?

 

Answer:

You need to turn on "hourly detail" and "minute detail". To do this:

  1. On the Dates tab, set the start and end dates up to cover the week you need.  

  2. On the Dates tab choose More Settings.

  3. Choose Hourly/Minute.

  4. Turn on Allow Hourly Detail and Allow Minute Detail.

 To have Milestones "snap to" a certain minute interval Choose Dates on the Tools tab.  Toward the bottom of this tab, choose one of the options for Snap To Minute Increment (5,10,15,30,60). For example, if you want to place symbols only every half hour, choose 30. If you want to be able to place symbols at 15 minute increments, choose 15.  Choose zero if every minute is needed.

 

 

 

 

 

 

 

 


 

 

 

 

 

 

 

 

 

Applies to Milestones Professional:      2017        2019         2021         2023         2025

 

   

   

   

   

 

 

 