Example: multi-file build and refresh

This example assumes there are three files (File1.MPP, File2.MPP and File3.MPP) which will used to create a single schedule which will later be updated (refreshed) from the 3 Microsoft Project schedules.

  1. Step 1 - Import File 1Step 1 - Import File 1:
      1. Choose Connections | Create Report from Project.

      2. Browse and locate the first Microsoft Project schedule (File1.MPP).

      3.  (The Microsoft Project to Milestones wizard includes these selections on the first screen).

      4. Use UniqueID (recommended) and enter file1 for the File nickname.

      5. Choose Use a built in template (or one of the other choices.)  Click Next in the wizard.

      6. Make selections in the wizard (for example Summary: Presentation Timeline and press Finish to create the schedule.

      7. Save the schedule as File1MilestonesSchedule.mlj.

     

  2. Step 2 - Import File 2Step 2 - Import File 2:
      1. Choose Connections | Create Report from Project.

      2. Browse and locate the second Microsoft Project schedule (File2.MPP).

      3.  (The Microsoft Project to Milestones wizard includes these selections on the first screen).

      4. Use UniqueID (recommended) and enter file2 for the File nickname.

      5. Choose Use a built in template (or one of the other choices.)  Click Next in the wizard.

      6. Make selections in the wizard (for example Summary: Presentation Timeline and press Finish to create the schedule.

      7. Save the schedule as File2MilestonesSchedule.mlj.

     

  3. Step 3 - Import File 3Step 3 - Import File 3:
      1. Choose Connections | Create Report from Project.

      2. Browse and locate the second Microsoft Project schedule (File3.MPP).

      3.  (The Microsoft Project to Milestones wizard includes these selections on the first screen).

      4. Use UniqueID (recommended) and enter file3 for the File nickname.

      5. Choose Use a built in template (or one of the other choices.)  Click Next in the wizard.

      6. Make selections in the wizard (for example Summary: Presentation Timeline and press Finish to create the schedule.

      7. Save the schedule as File3MilestonesSchedule.mlj.

     

  4. Step 4 - Create a new schedule (File1File2File3Merged.mlj)Step 4 - Create a new schedule (File1File2File3Merged.mlj)
      1. Open File1MilestonesSchedule.mlj.

      2. Save the schedule as (File | Save As...)  File1File2File3Merged.mlj.

      3. On the File tab, choose the next to Open.

      4. On the menu choose Chart to Merge.

      5. Locate File2MilestonesSchedule.mlj and open it.

      6. On the File tab, choose the next to Open.

      7. On the menu choose Chart to Merge.

      8. Locate File3MilestonesSchedule.mlj and open it.

      9. Save File1File2File3Merged.mlj

     

  5. Step 5 - Add a refresh list to File1File2File3Merged.mljStep 5 - Add a refresh list to File1File2File3Merged.mlj 
      1. On the Connections tab, choose the next to Refresh Previously Imported Project.

      2. On the menu choose Create/Edit Refresh File List.

      3. Click the Add Schedule button.

      4. Browse to locate File1.mpp and click Open.  

      5. The list now includes something like this:  <File1>C:\users\username\File1.MPP

      6. If the nickname (the <File1> in the example above) does not say File1, then

        1. Enter File1 in the Current File Nickname field.

        2. Click Press to Update Nickname.

      7. Browse to locate File2.MPP and click Open.  

      8. The list now includes something like this:  <File2>C:\users\username\File2.MPP

      9. If the nickname (the <File2> in the example above) does not say File2, then

        1. Enter File2 in the Current File Nickname field.

        2. Click Press to Update Nickname.

      10. Repeat steps 7-9 above to add File3.MPP with a nickname of file3 to the list.

     

     

  6. Save the File1File2File3Merged.mlj schedule.The schedule File1File2File3Merged.mlj can now be refreshed from the 3 separate Microsoft Project schedules.  

 

To refresh:

  1. Choose Connections | Refresh Previously Imported Project.

  2. There will be no prompt (as there usually is) to specify a Microsoft Project file from which to refresh.  Instead the Refresh Options dialog box will specify that the schedule is being refreshed from the schedule's refresh file list.


 

Related topics

Learn more about symbol tags.

Learn more about column and task row tags.

Learn how to build a free-form schedule tagged to Project.  

Show curves and bars in DataGraph

Legend and DataGraph Placement

 

 

 

 

 

 

 

Applies to Milestones Professional:      2017        2019         2021         2023         2025

 

   

   

   

   

 

 

 

The fast easy way to schedule your projects:  Milestones Software by KIDASA Software, Inc. www.kidasa.com

Copyright © 2025 KIDASA Software, Inc. All rights reserved.