Set percent complete for several tasks

Question:     

I really need to set the % complete for individual bars on my schedule.  I know I can set them on individual task rows and then roll them up, but frankly I really don’t want to set up an outlined schedule.  Is there any way to do this?

 

Answer:

Yes.  Here’s how:

  1. Right-click the start symbol of a bar.
  2. Choose Edit Size or Color.
  3. In the Override Bar Color section, set the Bar % Fill as shown:

 

 

Example:

 

 

 

 

 

 


 

Related topics

About showing progress in Milestones Professional    

Add a percent complete symbol in a column

Percent Complete pie color

Show percent symbol on a task row

Entered percent complete changes to different value    

Control the percent complete fill on a summary bar

 

 

 

 

 