Show a never-ending task

Question:     

I want to show that my task doesn't have an ending date.  It should have an arrow on the right to show that it continues into the future

 

Answer:

This is easy to accomplish.  Just customize your start symbol to be shape #28 (blank) and your end symbol to be shape # 43.  The example below also uses a shadow for both the bar and the end symbol.

 

 

 

 

 


 

Related topics