Question:     

I have this one schedule which is giving me fits.  For some reason, I am unable to change the start and end date range for the schedule.  Any ideas?

 

Answer:

It's likely that at some point you set individual date range overrides for one or more of the pages on your schedule.  

Remove page date range overrides:

  1. On the Dates tab, in the Start and End Dates section, choose More Settings...

  2. On the drop down menu, choose Page by Page Date Overrides.

  3. On the Schedule Details dialog box, click the Reset All button.    

         

 

 

 

 

 

 

 


 