Question:     

Usually when I go to refresh a Milestones Professional schedule from Project, I am asked to select the Microsoft Project file name.  I have one schedule (only one!) which never prompts me to select a file and I wonder what's going on.  Any ideas?

 

Answer:

It's likely that you (or someone else) set the one schedule up to use a Refresh List.  

Steps to clear the refresh list:

Check to see if there is a Microsoft Project file stored in the  schedule's Refresh File List.  If there is, then clear the refresh list.  

  1. Refresh file list is found on the Connections tab.  Select Refresh Previously Imported Project and then in the drop down choose Create/Edit Refresh File List.

  2. If there is a file in the list select it and then select Delete Schedule.

 

 

 

 

 

 

 

 


 

 

Related topics

Add a missing field from Microsoft Project

Add a tag to a symbol

Compare two files after refresh

Don't want to show unmatched Microsoft Project tasks in the refresh report   

Highlight changed dates when refreshing

Microsoft Project to Milestones Wizard refresh reports

No changes after schedule refresh

Symbol tags across multiple files

 

  1.  

 

 

 

 

 

 

Applies to Milestones Professional:      2019        2021        2023

 

 

 

 

      

The fast easy way to schedule your projects:  Milestones Software by KIDASA Software, Inc. www.kidasa.com

Copyright © 2023 KIDASA Software, Inc. All rights reserved.