Don't want to show unlinked Microsoft Project tasks in the refresh report

Question:     

I am updating my one page schedule from Microsoft Project using the refresh process.  Right now, at the bottom of the report I see thousands of Microsoft Project tasks which I am not using in my presentation report.  I would like to have the option NOT to show these.

 

Answer:

If Report missing Project tasks is un-checked, no unlinked tasks will be listed in the refresh report.

 

 

 

 

 

 

 

 


 

 