I am updating my one page schedule from Microsoft Project using the refresh process. Right now, at the bottom of the report I see thousands of Microsoft Project tasks which I am not using in my presentation report. I would like to have the option NOT to show these.
If Report missing Project tasks is un-checked, no unlinked tasks will be listed in the refresh report.