Filter to remove tasks which are 100% complete from view

Question:     

I would like to turn on a filter that would remove tasks that are 100% complete from the view. Is this possible?

 

Answer:

If you have a percent complete column, you can filter using that column.  

  1. Select the column using the arrow tool.

  2. On the Tools tab, choose Filter Task Rows.

  3. Choose Column Text Containing.

  4. In the Column Text Filter Selection dialog box, choose does NOT Include from the drop-down menu.

  5. Enter 100 in the box directly to the right of that drop-down choice.    

 

 

 

 

 

 

 

 


 