Import flagged Microsoft Project tasks only

Question:     

I have a lengthy Microsoft Project schedule, yet only want to display 50 or so tasks in Milestones. Can I import only flagged tasks from Microsoft Project?

 

Answer:

You can import filtered or flagged tasks from Microsoft Project.

  1. By default, only filtered tasks are imported into Milestones Professional.

  2. Most import choices allow you to choose a from Microsoft Project. Only flagged tasks are imported. 

After flagging selected tasks with Yes in Microsoft Project, choose the appropriate Flag field in the import wizard, as shown below: Only tasks with Yes in their Flag field will be imported into Milestones.

 

 

 

 

 

 

 

 

 


 

Related topics

Build and update a freeform schedule - Overview (Milestones Help)

Link individual symbols (Milestones Help)

Refresh process - Overview (Milestones Help)

Refresh from more than one Microsoft Project schedule (Milestones Help)   

Create Presentation Reports for Microsoft Project

Milestones to Project Q & A Roundup

Get list of all Project UIDs in Milestones schedule

Add a missing field from Microsoft Project

Difficulty connecting to Microsoft Project

 

 

 

 

 

 

Applies to Milestones Professional:      2019        2021        2023

 

 

 

 

      

The fast easy way to schedule your projects:  Milestones Software by KIDASA Software, Inc. www.kidasa.com

Copyright © 2023 KIDASA Software, Inc. All rights reserved.