Question:
I have tasks marked Inactive in Microsoft Project. When refreshing, I would like to be able to identify any symbols on my Milestones schedule which are linked to tasks which are inactive. How is this accomplished?

|
Answer:
A couple of options have been added to Milestones Professional 2025 to accommodate this.
For Inactive Project Tasks, Report to get a list of inactive tasks which are still on the schedule. Highlight to have all symbols linked to inactive tasks replaced with a ? symbol.

|