Inactive Microsoft Project tasks

Question:     

I have tasks marked Inactive in Microsoft Project.  When refreshing, I would like to be able to identify any symbols on my Milestones schedule which are linked to tasks which are inactive.  How is this accomplished?

 

Answer:

A couple of options have been added to Milestones Professional 2025 to accommodate this.  

For Inactive Project Tasks,  Report to get a list of inactive tasks which are still on the schedule.   Highlight to have all symbols linked to inactive tasks replaced with a ? symbol.