Insert a new task row on a schedule

Question:     

How do I add a new task row?

 

Answer:

  1. Select .

  2. Click in the column area to select the task you want to insert a task row before.

  3. Choose the task row option on the Insert menu.

-  or  -

 

  1. Select .

  2. Right click in the column area to select the task you want to insert a task row before.

  3. Choose Insert Task.   

 

 

 

 

 


 