On this screen of the Project to Milestones Wizard, it is possible to specify the symbology for the schedule. Two choices are available on this screen.
Symbology Type: Several choices are available for content of the schedule area:



-
Gantt bars - spacesaver: Milestones will attempt to fit as many tasks on a row as possible for each outline level. (If a summary bar has 10 tasks and they are sequential, they will appear on one row. If they are not sequential, several rows will be used but typically fewer than 10).

-
Gantt bars - custom symbology: Choose this option and a customize button will appear for picking the symbols and dates to import. The recommended choice for custom symbology.
-
Gantt bars - custom symbology2: In previous versions, this was referred to as Gantt bars-custom. Not the recommended choice for custom symbology.
-
Milestones - condensed finish dates: Finish dates only will appear on summary bars. Start and Finish dates are be shown.




|