Microsoft Project timescaled (timephased) earned value fields

If a Microsoft Project schedule includes baseline and cost information, then the Project to Milestones Wizard will be able to generate earned value graphs using timescaled values from Microsoft Project.

Timescaled values are picked up from the Microsoft Project top level summary.  

The built in templates which include the word timephased will bring in the Microsoft Project timescaled values.

It is also possible to bring in limited information from Microsoft Project (Baseline Cost, % complete and Actual Cost) and have Milestones Professional calculate earned value.

 

 