Microsoft Project to Milestones Professional wizard refresh reports

Question:     

When we do a refresh from Microsoft Project, is there a way to get a report of all  changes?

 

Answer:

You can have Milestones highlight the changed dates along with the report that is automatically generated.  When generated, the results are shown in a dialog box and are also available on the clipboard to paste into another application.

 

 

 

 

 

 

 

 

 


 

 

Related topics

Add a missing field from Microsoft Project

Add a tag to a symbol

Compare two files after refresh

Don't want to show unmatched Microsoft Project tasks in the refresh report   

Highlight changed dates when refreshing

No changes after schedule refresh

Symbol tags across multiple files

Build and tag a schedule for refresh

Link a symbol to Microsoft Project

  1.  

 

 

 

 

 

 

 

 

Applies to Milestones Professional:      2017        2019         2021         2023

 

   

   

   

   

 

 

 

The fast easy way to schedule your projects:  Milestones Software by KIDASA Software, Inc. www.kidasa.com

Copyright © 2021 KIDASA Software, Inc. All rights reserved.