Report on schedule data

Generate reports on data embedded in symbols, overall schedule data, and earned value calculations.

Generate a report by selecting  Tools | Reports

Each report can be copied to the clipboard for pasting into another program for printing.

Symbol Reports:

  • Symbol Notes Report  -  displays data for each symbol which contains text in its symbol notes field, including the task row on which the symbol appears, the symbol's ordinal placement from left to right along the task row, the symbol's date, and the text of the symbol Notes. Optionally, data from one to all schedule columns may be included, and hidden rows may be ignored if needed.

  • Symbol to Symbol Links Report -  displays data for each symbol which has an outgoing link to another symbol (used for symbol linking), including the task row on which the symbol appears, the symbol's ordinal placement from left to right along the task row, the symbol's date, the name of the symbol to which it is linking, and the full path to the file containing the named symbol.

  • Symbol Names Report - displays data for each symbol which has a target name (used for symbol linking), including the task row on which the symbol appears, the symbol's ordinal placement from left to right along the task row, the symbol's date, and the symbol's link target name as found under the Symbol Links tab.

  • Symbol Tags  -  displays data for each symbol which has an automation tag, including the task row on which the symbol appears, the symbol's ordinal placement from left to right along the task row, the symbol's date, text and automation tag text.

  • Symbol Attributes - displays data for each symbol which has either a hyperlink, note, outgoing link, name, or tag. The information displayed includes the task row on which the symbol appears, the symbol's ordinal placement from left to right along the task row, the symbol's date, and the symbol's attributes.

Schedule Reports:

  • Hyperlinks Report -  displays data for each symbol or task row which has a hyperlink, including the task row on which the symbol appears, the symbol's ordinal placement from left to right along the task row, the symbol's date and the full path to the hyperlinked file.

  • Holiday Report - displays holiday information, including whether holidays are global or embedded, and the dates and number of holidays.

Earned Value Reports:

  • Estimate at Completion -  shows each type of EAC as a bar graph, including "Overrun to Date" method, "Cumulative CPI" method, and "CPIxSPI" method of EAC Calculation.

                 

  • CPI Report -  shows CPI for the current schedule on a line graph.

                

  • CPI with TCPI Report - shows CPI and TCPI for the current schedule on a line graph.

                

  • SPI Report - shows SPI for the current schedule on a line graph.

                

  • Actual Cost/Planned Value/Earned Value Report - The Actual Cost/Planned Value/Earned Value Report shows a bar graph with each of the above values displayed horizontally:

                

  • EV Schedule Status Report - this report shows the overall schedule status:

                

  • EV Dashboard Report - this report displays all 6 EV reports together.

       

 

 

 

  