Answer:Milestones Professional has a feature called Shift All Dates which will let you move all schedule dates (including curtains, if any) into the future (or past) by any number of days. Example: Original Schedule Example: Schedule shifted 600 days This option is handy for those working on project proposals. Schedules can be put together without knowing what the schedule starting date will be. Then, when the project start date is known, just shift the schedule to that date.
Shift all symbols by a number of days:
Shift all symbols by a number of days, on selected task rows only:
|
|
Move all symbols on a row back by the same amount of time Shifting symbols, values, and curtains
|
Applies to Milestones Professional: 2017 2019 2021 2023