Show date and text on same line for a symbol

Question:     

I have a few symbols on my schedule for which I would like to display both the start date AND the text on the same line on the left side of the symbol.  Is there a way to combine the symbol text and the date?

 

Answer:

Yes, this is possible by using the &date substitutable string as part of the symbol text.

  1. Hide the symbol date by setting the Vertical Date Placement to Hide.  (see figure)
  2. Set the Text Placement for the symbol text to Middle and Left.
  3. In the Line 1 field for the symbol text, add &date to the symbol text string. This will cause the date to display along with the text.  

 

 

 

 

 

 

 


 

Related topics

Show date and text on one line with two colors

Show symbols above or below the bar

Show text at an angle

Add a date below symbol text

Move symbol text easily

 

 

 

 

 

 

Applies to Milestones Professional:      2019        2021        2023

 

 

 

 

      

The fast easy way to schedule your projects:  Milestones Software by KIDASA Software, Inc. www.kidasa.com

Copyright © 2023 KIDASA Software, Inc. All rights reserved.