Question:     

Is there a way to view the unique id's you have linked in your milestone chart?

I have a rather large schedule.  I am trying to see a report or search for a Unique ID that is linked to my project.  Task Unique ID 144 for example.  I have a couple hundred symbols linked and I want to find the symbol that 144 is linked to.

 

Answer 1 - Use the Symbol Tags Report:

  1. Choose the Tools tab.

  2. In the Reports section choose Symbol.

  3. From the drop down menu, choose Symbol Tags as shown here:

Answer 2 - Use the find tool:

  1. Choose the Edit tab.

  2. In the Find, Replace, Go to.. section choose Find.

  3. From the drop down menu, choose Symbol Tags Only and enter a Unique ID in the Find What space as shown here:  

 

 

 

 

 

 

 

 


 

 

Related topics

Create Presentation Reports for Microsoft Project   

Milestones to Project Q & A Roundup

Get list of all Project UIDs in Milestones schedule

Add a missing field from Microsoft Project

Difficulty connecting to Microsoft Project

Import from Microsoft Project (Milestones Help)

Build and tag a schedule for refresh (Milestones Help)

Link a symbol to Microsoft Project (Milestones Help)

 

 

  1.  
 

 

 

 

 

 

Applies to Milestones Professional:      2019        2021        2023

 

 

 

 

      

The fast easy way to schedule your projects:  Milestones Software by KIDASA Software, Inc. www.kidasa.com

Copyright © 2023 KIDASA Software, Inc. All rights reserved.