Answer:This is the status line. The status line shows at-a-glance ahead/behind status. It extends vertically along the current date line. The status line bulges to the left or right according to each task row's status date. Thus, the status line is a visual indicator of ahead/behind status. To turn it off, just go to the Dates tab and
|
|