Red line on schedule

Question:     

What is the red line which seems to go in and out from the current date line?

 

Answer:

This is the status line.  The status line shows at-a-glance ahead/behind status.  It extends vertically along the current date line. The status line bulges to the left or right according to each task row's status date. Thus, the status line is a visual indicator of ahead/behind status.

To turn it off, just go to the Dates tab and Status Line.

 

 

 

 

 

 

 

 


 

Related topics

Automatically update % complete on a bar

Why are my symbols hollow?

Change the shape of a symbol based on status

Difference between status line and current date line  

Need today's date plus status date

Remove line in middle of bar

 

 

 