Answer:These symbols and connectors are filled to the status date, meaning they are solid before the status date (usually the current date) and hollow after the current date. In Milestones Professional, bars and symbols may have after status colors set.. To change this: On the Dates tab: This example shows the schedule with Fill to Status Date turned on. Notice the hollow symbols and connectors.
This example shows the schedule with Fill to Status Date turned off. Notice the symbols and connectors are filled in past the current date line.
|
|
Control the percent complete fill on a summary bar What can affect Fill to Status Date? Why are some symbols not filled? About showing progress (Milestones Help) Fill symbols/bars to status date (Milestones Help) |