Status Stoplight |
||||||||||||||||||||||||
|
This format uses the Microsoft Project Status field and imports that information into a column on the right side of the Milestones schedule area. Milestones converts the Microsoft Project status field information into indicator symbols:
The schedule is built using these Microsoft Project fields: Start, Finish, Baseline Start and Baseline Finish. This schedule can be customized and saved as a custom template. This format can not be refreshed.
|
||||||||||||||||||||||||
Slipping Tasks |
||||||||||||||||||||||||
|
This Import Wizard choice produces: "On the left, Task Name, Baseline Start, Start, Baseline Finish, Finish The schedule shows tasks which are behind schedule.
|
||||||||||||||||||||||||
Unstarted Tasks |
||||||||||||||||||||||||
|
The Unstarted Tasks report displays all tasks which do not have an actual start date. A chart is produced showing the WBS # and Task name in the left columns. To the right of the schedule, indicators will show whether a task is critical and also whether or not the task is late.
|
||||||||||||||||||||||||
Status Line |
||||||||||||||||||||||||
|
This Import Wizard choice produces: On the left, Task Names On the right, Percent Complete Status Line is drawn to illustrate % complete (status) for each task.
|
||||||||||||||||||||||||
Top Level Tasks |
||||||||||||||||||||||||
|
This Import Wizard choice produces: On the left: WBS and Task Name. On the right, Schedule and Cost indicators as shown in the legend, plus a %complete Pie Indicator column." This schedule can not be customized and saved as a custom template. This format cannot be refreshed.
|
||||||||||||||||||||||||
Weekly Status Report |
||||||||||||||||||||||||
|
Weekly Status Report, provides a simple format with easy to read information for a quick status of multiple tasks.
|
||||||||||||||||||||||||
Cost Account Plan |
||||||||||||||||||||||||
|
This is a common defense industry format which can be easily customized to meet reporting requirements. Column on the left: 1) Name, Finish, Baseline Finish, Finish Variance Columns on the right: BCWS, BCWP from Microsoft Project Graph: Timescaled PV and EV (BCWS and BCWP) from Microsoft Project
|
||||||||||||||||||||||||
Project Status Report |
||||||||||||||||||||||||
|
This Import Wizard choice produces: Left Columns - WBS, Task Name Right Columns - Duration, Remaining Duration, Remaining Duration%, Cost, Remaining Cost, Remaining Cost %, Resource Names. Baseline start/finish and start/finish are shown |