WBS stands for Work Breakdown Structure. WBS Numbering is used in conjunction with outlining. Once a schedule has been outlined, a column can be set up as a WBS SmartColumn. Milestones Professional will then automatically fill in the WBS numbers which correspond to the outline levels.
Add a WBS SmartColumn to the schedule:
Click once on the column heading to change its title and other properties in the Selection menu. Alphanumeric WBS NumberingThe WBS hierarchy can contain letters as well as numbers. For example, a task with a WBS of 1.1.1 can be formatted to read 1.a.1, or A.1.1, or a.a.A, etc. In the dialog that appears when a WBS SmartColumn is defined, levels 2, 3 and 4 are checked to indicate that letters should be used.
ExampleIn the example below, WBS levels 2, 3 and 4 display a capital letter.
|