Duration values for single milestones

Question:     

Why does a single milestone automatically have a 0-day duration instead of 1 day?

 

Answer:

 

If Schedule Details does not allow Hourly or Minute detail, then a single Milestone will show 0 duration.  However, for a milestone to show 1-day duration, or a specific hourly duration, Schedule Details must allow at least Hourly detail.

  1. Choose More Settings in the Start and End Dates section of the Dates tab.

  2. Choose Hourly/Minute...  

  3.  Allow Hourly Detail and Allow Minute Detail.


 

Related topics

Duration on a summary bar

 

 

 

 

 

Applies to Milestones Professional:      2019        2021        2023        2025

 

 

 

 

      