Duration on a summary bar

Question:     

I have a duration column.  On the summary bar, the duration appears to be the total of the lower level durations.  I don't want the cumulative duration of all the tasks but the duration from the start of the first task to the completion of the last task.

 

Answer:

Here's how to get what you want on the summary bar:

  1. Double-click the column heading of your duration column.  This brings up the Column Properties dialog box.

  2. Choose the Properties button.

  3. On the Duration Settings dialog box,  Show Summary Duration in Calendar Time:  

 


 

 

Related topics

Duration values for single milestones

 

 

 

 

 

Applies to Milestones Professional:      2019        2021        2023        2025

 

 

 

 

      

The fast easy way to schedule your projects:  Milestones Software by KIDASA Software, Inc. www.kidasa.com