Reschedule a task

Question:     

Is there an easy way to reschedule a task (start symbol, bar, end symbol) to another date without individually moving the symbols?

 

Answer:

Using "Shift All Dates" you can move all symbols and connectors forward or backwards.

  1. From the Edit menu, choose Shift All Dates.

  2. Enter the number of working days you want to shift all symbols and connectors and indicate whether you want it to be shifted forward or backward.  

  3. You have an additional choice to shift the schedule date range's start date an equal amount.

 

To move only selected tasks:

  1. Use the Arrow tool to select tasks you want to move ahead or behind in time.

  2. Choose Shift Dates for Selected Tasks on the Edit menu.

  3. Enter the number of working days you want to shift those symbols and connectors and indicate whether you want it to be shifted forward or backward.  

 

 

 

 

 

 


 

Related topics

Shifting symbols, values, and curtains

Show 20 day time periods

Shift all dates

Show a never-ending task

 

 

 

 

 

 

 

Applies to Milestones Professional:      2017        2019         2021         2023         2025

 

   

   

   

   

 

 

 

The fast easy way to schedule your projects:  Milestones Software by KIDASA Software, Inc. www.kidasa.com

Copyright © 2025 KIDASA Software, Inc. All rights reserved.