Find a task row

Question:     

How do I add column data that shows me the "Task Row" that my milestone/bar is on? In "Symbol Properties" I can open tab "Vertical Links" to see that I have connected my milestone to "Task Row 403" but I have no way of finding that row.

 

Answer:

Milestones Professional has quite a few SmartColumn types, including the Task Number column.  

  1. On the Insert tab, click Rows|Columns|NewColumn
  2. From the list, pick Task Number...
  3. Click OK on the dialog box.

 

 If a schedule is quite large, using the Vertical Links report can be helpful.  Click Tools | Reports | Symbol | Vertical Links... to get a report of all symbols on a schedule which have either an incoming or outgoing vertical link.

 

 

 

 

 

 

 

 


 

Related topics

Task row height adjustment

Insert a column