Question:     

I am trying to bring tasks into my Milestones schedule from Project server.  I'm not getting any errors, but nothing is coming in.

 

Answer:

Be sure that the two check boxes indicated are checked.  If they aren't checked, the task is tagged, but no symbolsare added to the schedule.

 

 

 

 

 

 

 

 


 