The Percent Complete view mode replaces the Gantt bars and milestones with bar graphs indicating each task's percent complete. Each task displays a red bar (default setting) indicating its percent complete. A bar's length corresponds to a task's percent complete value in relation to the date heading length. That is, a task which is 50% complete will display a red bar which traverses half of the date heading's length. The percent complete bars do not represent start and stop dates. To display the Percent Complete view, choose View | Viewing Options | Chart Type: Gantt-Percent Complete. Example: This schedule represents a typical Gantt view.
When switched to Percent Complete view, each task displays a red bar and value indicating its percent complete. Options for the Percent Complete view can be found on the Tools tab. Choose Tools | Program Options | General.
Cycle through toolbox bar colors:This option produces a more colorful percent complete view, using the colors from the schedule's toolbox. To adjust the colors, just adjust the colors of the bars in the toolbox.
Bar size:The bar size can be normal, medium or large. Small:
Medium:
Large:
Include text from column:To display text on the percent complete bar, just pick a schedule column. Alternate percent column:By default, the task's percent complete column is used. An alternate Values column can be selected.
|
The fast easy way to schedule your projects: Milestones Software by KIDASA Software, Inc. www.kidasa.com
Copyright © 2023 KIDASA Software, Inc. All rights reserved.