Workday start and end times must be defined if hourly and/or minute detail is turned on, for accurate duration calculations. If duration calculations need to be accurate only to the day, then there is no need to define Workday Time. When the Hourly/Minute tab on the Schedule Details dialog box is chosen, there is Start Time 1/End Time 1 and Start Time 2/End Time 2 in the Workday Time box. This box enables calculations of durations for split shifts. For example, a company’s typical day may include an 8 a.m. to 12 p.m. shift and a 1 p.m. to 5 p.m. shift. Because no work is done between 12 p.m. and 1 p.m., there is a choice not to include that time in the duration calculations. Set workday start and end times:
|