Answer:This will only happen if
Since there is no activity before the current date, Milestones has no choice but to allocate the funds after the current date. Reasonably, a task which is in the future and has no progress (zero % complete should have no actual cost. To display a graph which accurately shows $ spent before the current date, 1) Choose the Allocate to current date option for the ValueSet and 2) Be sure that tasks which are in the future have a value of zero.
|
Applies to Milestones Professional: 2019 2021 2023