Refresh a schedule from Project with a percent complete field other than standard percent complete

Question:     

I want to refresh my presentation schedule with Physical Percent Complete (instead of percent complete).  I can't find any setting for this.  No matter what I do, refresh always uses percent complete.

Question:

Hello - I am working on a Milestones Professional schedule and am wondering if I can map the bar complete fill to another column in Microsoft Project. My understanding is that the bars currently fill based on the % Complete column data in the Microsoft Project file. I would like to use another Microsoft Project field that we use for Earned Value % Complete. Is that possible?

 

Answer:

On the Milestones Refresh Options screen, make selections similar to the following:

 

 

 

 

 

 

 

 


 

 

Related topics

Add a missing field from Microsoft Project

Add a tag to a symbol

Compare two files after refresh

Don't want to show unmatched Microsoft Project tasks in the refresh report   

Highlight changed dates when refreshing

Microsoft Project to Milestones Wizard refresh reports

No changes after schedule refresh

 

 

 

 

 

Applies to Milestones Professional:      2019        2021        2023

 

 

 

 

      

The fast easy way to schedule your projects:  Milestones Software by KIDASA Software, Inc. www.kidasa.com

Copyright © 2023 KIDASA Software, Inc. All rights reserved.