When "bar fill to status date" is active, the summary bar is filled to match the percent complete of the sub-tasks. As shown below in the red circle, Project B's fill-to-status goes beyond the current date line because the bar's fill is based on the percent compete, not the current date line. The 85% complete value is calculated as the total completed duration of the Activities divided by the total overall duration of the Activities for Project B. Additional explanation:The value in a Percent Complete SmartColumn for the Summary Bar row is computed by adding all the completed duration of the sub-tasks and dividing by the total duration of all the sub-tasks. This percentage value is then used to control how much of the Summary Bar is filled in.
Override the summary bar status fill:Use a status symbol to control the portion of the summary bar that is filled. By creating a status symbol and placing it on the summary bar row, it's possible to force the bar to fill to the status symbol. Thus, it is possible to fill the summary bar to the current date or any other date independently of the percent complete value.
Force the summary bar to fill to the current date:
Completely fill summary bars:
|
Related Topics
The fast easy way to schedule your projects: Milestones Software by KIDASA Software, Inc. www.kidasa.com
Copyright © 2025 KIDASA Software, Inc. All rights reserved.