Tips & Tricks for June 2024

(Click the question title for the answer)

I have this one schedule which is giving me fits.  For some reason, I am unable to change the start and end date range for the schedule.  Any ideas?

I have my symbols vertically linked and they are not moving as expected

I have a schedule and MPS that I have an issue with updating. The schedule is tagged to the MPS but the MPS is not updating.

Could you explain the purpose of the "or Column tag of Override Fill Color" feature in the Symbol Properties>Size/Color/Summary menu, and how to use this feature? I'm unable to find any information on it in either the User Manual.

My symbol text is spaced too far away (vertically) from my bar. 

How can I adjust the height of a task row?  How do I reset the height to its original setting?

Can I easily switch to another time period?

We have a Milestones Professional plan linked to Microsoft Project.  Is it possible to show the % complete from Microsoft Project if there is more than one bar per row?  I have read various documents in the Knowledgebase but haven't seen any document that indicates whether this is possible.

How do I get rid of my page breaks so that Milestones just puts the same number of tasks on each page?

Is there a way to increase the size of the tool box? it is too small to see what symbols I need to use. I'm using a very high res monitor.

 

 

 

 

 

 

 

Applies to Milestones Professional:      2017        2019         2021         2023         2025

 

   

   

   

   

 

 

 

The fast easy way to schedule your projects:  Milestones Software by KIDASA Software, Inc. www.kidasa.com

Copyright © 2025 KIDASA Software, Inc. All rights reserved.