Highlight changed dates when refreshing

Question:     

Is it possible to highlight the milestones which have changed after running a Milestones refresh to update my presentation schedule with dates from Microsoft Project?


Question 2:

I refreshed my schedule and choose the option to highlight the changes.  Now, how do I turn off the highlighting?

 

Answer:

Yes.  On the Milestones Refresh Options dialog box, there is an option Highlight Changed Dates.  If this option is checked then when the refresh is done, changed items will be highlighted as shown in the example below.

To turn the highlighting on/off there is a toggle available on the Connections tab on the toolbar.

 

 

 

 

 

 

 

 


 

 

Related topics

Add a missing field from Microsoft Project

Add a tag to a symbol

Compare two files after refresh

Don't want to show unmatched Microsoft Project tasks in the refresh report   

Highlight changed dates when refreshing

Microsoft Project to Milestones Wizard refresh reports

No changes after schedule refresh

Symbol tags across multiple files

 

 

  1.  

 

 

 

 

 

Applies to Milestones Professional:      2019        2021        2023        2025

 

 

 

 

      

The fast easy way to schedule your projects:  Milestones Software by KIDASA Software, Inc. www.kidasa.com

Copyright © 2023 KIDASA Software, Inc. All rights reserved.