Tips & Tricks for September 2024

I need to copy some symbols on one schedule to another schedule.  How can I do this?

Is there a quick way to remove all links to any and all milestones in your file quickly, without having to go to each milestone?   We’d like to strip off all links associated with milestones within a file and any short names we’ve given or placed on a file.

I have a row with many milestones (20 or so).  I would like to calculate the difference between two specific milestones on each row of my schedule.  (Start up date and First Delivery Date) Any ideas?

Is there a way to get a summary of how many times each toolbox symbol has been used?  I need to identify which symbols in the toolbox have been used the least.

I have a row with many milestones (20 or so).  I would like to calculate the difference between two specific milestones on each row of my schedule.  (Start up date and First Delivery Date) Any ideas?

I would like to change the default location where charts are saved.  How can I do this?

I want to change the font size of all symbols at once.

I notice that the Milestones schedules all have different toolboxes.  Can I customize my toolbox so that when I create new schedules, I always start with the same toolbox?

We are trying to import a spreadsheet from Excel to Milestones. We have correctly mapped the dates to the proper fields, yet the start and finish dates are not appearing in the Milestones schedule. What is the solution?

In the Date Heading area: is there a way to make the background color dark and the divider lines lighter?   

I only want to show the date in the Start and End date columns.  Right now, I see the date plus the time.  Is there a way to hide the time?

How can I get more rows on one page?  I want to get everything on one page.  Right now I have 16 tasks but 4 are on a second page.

When I increase the outline level of a task, the column text automatically indents, and the text no longer fits in the cell.  How can I prevent this?